Point Isabel ISD District Construction and Renovations
Juliette Gonzalez-Ba
Created on September 26, 2023
More creations to inspire you
SEVEN WONDERS INFOGRAPHIC
Horizontal infographics
7 CONTINENTS
Horizontal infographics
A2 - ABENTEUER AUTOBAHN
Horizontal infographics
STEVE JOBS
Horizontal infographics
OSCAR WILDE
Horizontal infographics
TEN WAYS TO SAVE WATER
Horizontal infographics
NORMANDY 1944
Horizontal infographics
Transcript
90.69% Complete
Phase 2
All Campuses Staff Lounge/RestroomsHigh SchoolAuditoriumJunior High Locker room, Stage, Life Skills Classroom
100 % Complete
Phase 1
Derry and GarrigaRestrooms
53.86% Complete
Phase 3
Elementary SchoolsOutdoor Basketball Courts, Outdoor Learning Center, Playgrounds (ADA Complaint) & Playground Canopies, Walking TrailsJunior HighWalking Trail, Outdoor Learning CenterHigh SchoolWalking Trail, Outdoor Learning Center
19.78% Complete
Phase 4
High School New ConstructionCTE Building
District Construction and Renovations
+info
Info
Gallery
Phase 3
Start Date: January 2023Completion Date: August 2023
Elementary Schools –Outdoor Basketball Courts, Outdoor Learning Center, Playgrounds (ADA Compliant)& Playground Canopies, Walking TrailsJr High – Walking trail, Outdoor Learning CenterHigh School – Walking trail, Transition Learning Center (located at Jr High)Notice to Proceed – June 20, 2023Days to complete: 240 calendar daysSubstantial Completion Date: February 21, 2024
Progress
Contractor: Gerlach Construction
+info
Info
Phase 1
Start Date: January 2023Completion Date: August 2023
Derry & Garriga Student RestroomsNeeds more data
Progress
Contractor: Gerlach Construction
+info
Info
Phase 2
Notice to Proceed – Monday, April 3, 2023Days to complete: 180 daysSubstantial Completion Date: September 30, 2023
All Campuses - Staff Lounge/RestroomsHigh School- Auditorium Jr High - Locker Rooms, Stage, Life Skills Classroom
Progress
Gallery
Contractor: Gerlach Construction
Notice to Proceed – June 20, 2023Days to complete: 365 Calendar DaysSubstantial Completion Date: June 25, 2024
Phase 4 – New ConstructionProject:CTE Building
Progress
Gallery