Presentation of the Project

architectural Model

Thermal loads

energy balance

03

04

01

02

Construction of a medical house of 200m2 in Couffouleux in the 81. This building includes 4 offices (treatment rooms), 1 reception, 1 waiting room and private areas.

01. Presentation of the Project

Project Context

01. Presentation of the Project

Localization

Study and optimize the heating and air conditioning installation of the building

Optimize the energy consumption of the building by GTB-GTC
Etudy of a photovoltaic installation

Objective of the Project

01. Presentation of the Project

common Part

Personal part

01. Presentation of the Project

Analysis of the DCE

Collaborative Work Platforms

Composition of walls

01

Composition of the partitions

02

Composition of the dubbing

03

Insulation composition

04

Type of ventilation

05

02. Architectural Model

Architectural Model Design (REVIT)

02. Architectural Model

Architectural Model Design (REVIT)

02. Architectural Model

outside air intake

the use of each room

the compositions of the carpentry

the compositions of the walls

03. Thermal Loads

CYPETHERM LOAD

12.5%

12.8%

13.3%

Bureau 1

Bureau 3

Accueil

Bureau 4

+ ino

Salle de repos

Bureau 2

Salle d'attente

7.4%

9.6%

12.2%

12.3%

19.8%

Secrétariat

856 W

910 W

876 W

505 W

1356 W

833 W

659 W

844 W

12.3%

12.7%

16.1%

Bureau 1

Bureau 3

Accueil

Bureau 4

Salle de repos

Bureau 2

Salle d'attente

7.2%

9.1%

11.6%

11.8%

17.6%

Secrétariat

1601 W

2096 W

1658 W

938 W

2297 W

1511 W

1180 W

1539 W

6839 W

13023 W

Cooling Loads

Heating Loads

03. Thermal Loads

04. Energy Balance

Energy Consumption of the Building

Energy Requirement of the Building

Cef Chauffage : 28.80 kWh/m2/an

Cef Refroidissement : 21.30 kWh/m2/an

Cef Auxilliaire Ventilation : 15.60 kWh/m2/an

Cef Auxilliaire Distribution : 2.4 kWh/m2/an

Cef TOTAL : 68.10 kWh/m2/an

Besoin Chauffage : 29.30 kWh/m2/an

Besoin Refroidissement : 26.60 kWh/m2/an

Besoin TOTAL : 55.90 kWh/m2/an

Partie Individuelle

1

2

3

Etude Climatisation

Etude Dimensionnement

Réalisation du Devis

4

Planning d'Intervention

5

Comparatif

01. Etude Climatisation

Présentation des travaux

02. Etude de Dimensionnement

Mon Choix : Daikin Altherma 3 M R32

Charges thermique du Bâtiment : 13.023 kW

Puissance Daikin Altherma 3 M : 10.82 kW

Ajout Appoint électrique : 3 kW

Puissance TOTALE : 13.82 kW

02. Etude de Dimensionnement

Mon Choix : Daikin Altherma 3 M

01

Un seul ventilateur

02

Système Monobloc au r-32

02. Etude de Dimensionnement

Rapport de Solution de Chauffage

02. Etude de Dimensionnement

Rapport de Solution de Chauffage

02. Etude de Dimensionnement

Choix Ventilo-Convecteurs

Pourquoi Daikin Altherma HPC

la discretion :





le debit d'air modulé :

02. Etude de Dimensionnement

Dimensionemment Ventilo-Convecteurs

02. Etude de Dimensionnement

Sélection Ballon de Découplage

Principe Fonctionnement Ballon Découplage

02. Etude de Dimensionnement

Plans de Réseau

03. Réalisation du Devis

04. Planning d'intervention

05. Comparatif

PAC air/eau ou PAC air/air ?

COP

PRIX

DISCRETION

3.70

4.87

+/- 20 000 euros

+/- 30 000 euros

24%

Conclusion

Remerciement